Meeting documents
- Meeting of Resources Overview Committee, Wednesday, 21st June, 2017 6.30 pm (Item 9.)
Minutes:
The Committee
was updated on the current position regarding the development of the Amersham
Multi Storey Car Park to provide a total of 1,046 car park spaces, an increase
of 366 on the current 680 spaces. The project was to be put before the Planning
Committee on 22 June 2017.
It was
highlighted that the existing car park was running at full capacity throughout
the week with up to 80 cars often being turned away daily. These cars then take
up spaces in the town centre which in turn affected the local trade.
Detailed costs
were outlined in the report and appendices and detailed breakdowns were
available. The Committee were advised that the total cost noted was the total cost
certainty that the selected contractors would sign up to. A recent capacity
survey had recommended that by 2036 additional spaces of between 339 and 520
were required to meet anticipated growth in rail travel and housing.
Should the
project go ahead a loan would be taken out through the Public Works Loan Board
to fund this project which would take approximately one year to complete. A
detailed income and expenditure was provided in the reports pack and the
Committee were advised that the project would cover its costs and provide an
income over a 40 year period. Estimates had been cautious due to the small risk
of the car-park not being used to a high capacity. Modelling on various
scenarios to show potential income could be seen in Appendix C.
Mark Jackson,
Balfour Beatty took the Committee through the procurement and pre-construction
process and reassured the Committee that site investigations, intrusive
surveys, market test of demand, and design team meetings had all been
completed. 100% cost certainty on Tender price had been achieved.
The item was
discussed at length and the Committee were invited to make comments to be taken
in to consideration by Cabinet. Issues highlighted included:
a)
The
Committee requested clarity on item 4.4 of the report which noted the costs of
the additional deck and further 126 spaces as £591,000 which appeared to be
accounted for in the total £8.8m although was listed separately through other
sections of the report.
b)
The
£313k scheduled for relaying the surface on the top floor of the existing car
park was included in the overall cost of the new car park.
c)
The
Committee were advised that the Public Works Loan Board changed interest rates
daily. It was confirmed that as soon as the loan was taken out, the rate would
then be fixed for the life of the loan. Whilst rates had been stable for the
last six months the Committee were advised that were approval given the rate
would be secured as soon as possible to avoid potential interest rate
increases.
d)
A
detailed risk analysis had been completed and risks mitigated. The lifespan of
materials used was in excess of 40 years.
e)
Staff
parking had been reviewed with staff now able to use the additional capacity
created at the Sycamore Road car park to alleviate some of the pressures on the
Multi-Storey car park.
f)
The
total cost per space had increased significantly when the fourth storey of the
car park was added. This increased significantly to factor in progressive
collapse territory.
g)
In
terms of parking charges being increased in line with inflation it was
explained that an annual rise of 3% was not expected but over time there was
capacity to increase charges in line with inflation. The Committee required
further clarification around the sensitivity of the figures to different
assumptions about charges increases.
h)
The
unforeseen project risk figure noted was explained, this would cover any
potential further work required by TfL; any
archaeology discovered during excavations and any judicial review costs. These
were all felt to be highly unlikely
RESOLVED
1. That the draft Cabinet report be noted
and the comments of the Resources Overview Committee be forwarded to the
Cabinet.
2. Clarification on the pre-construction costs of £591k and the total
overall costs be provided prior to the meeting of Cabinet
on 27 June 2017.
3. Clarification on parking charges in relation to annual inflation be provided prior to the meeting of Cabinet on 27 June 2017.